PROJECT DESCRIPTION

As a result of Columbia Gas’s disturbance to public roads and sidewalks during the gas emergency and gas restoration last fall, the Town will be undertaking restoration and paving of approximately 15 miles of roadway. Public Works will be responsible for overseeing the road/sidewalk restoration project. The project is estimated to take 4 years, however with good project coordination, a large portion of work will be completed in advance of this time frame. 

Road paving selection and schedule will follow a similar objective process as found in our annual Roads Program, however we will be taking a neighborhood approach such that roads in the same vicinity will be grouped/paved together in order to minimize disruptions to residents/businesses. Paving schedule will be heavily weighted on coordination with several ongoing Town/State projects. 

As we move forward with developing the schedule for all roadwork, we will conduct public information meetings to receive input, review alternatives and communicate project plans. As the project progresses, we will also make full use of the Town’s website and social media accounts to provide timely information to residents/businesses. 

CONSTRUCTION UPDATE

CONTRACT 2A - UPDATE

 

Cassidy Landscaping has completed the replanting program for the Contract 2A area.    A total of 120 new trees were replanted through the Contract 2A area.   Any residents wanting to discuss the tree replanting program should call Elaini Sahtouris, Staff Engineer at 978-685-0950 x.44022. 


 

CONTRACT 3-4-5

 

PJ Albert has started milling of the roads within the Contract 3-4-5 areas.  Milling is anticipated to take approximately 5 days and will be complete on Tuesday May 7, 2024, weather permitting.  Following milling, PJ Albert's subcontractor will begin to raise castings.  Raising of castings is expected to take one week.  


PJ Albert's subcontractor MTK is scheduled to begin installing concrete handicap ramps  on May 8th, 9th, and 10th.


Roadway paving is tentatively scheduled to begin the week of May 13th or May 20th pending the progress of raising the castings and installation of handicap ramps.



Residents have been asking about tree planting within the Contract 3-4-5 areas.  Tree planting is one of the last items done so no new trees are damaged during construction.  Once PJ Albert finishes the restoration activities at the end of the Summer 2024, tree replanting in the Contract 3-4-5 areas will begin.  Any residents wanting to discuss the tree replanting program should call Elaini Sahtouris, Staff Engineer at 978-685-0950 x.44022. 

Please continue to email at road-restoration@northandoverma.gov or call the DPW at 978-685-0950 with questions, comments, or suggestions.


CONTRACT 2 AREA MAP

CONTRACT 3-4-5 STREET LISTING

CONTRACT 2 STREET LISTING

CONTRACT AREAS

CONSTRUCTION PHOTOS

PROJECT UPDATES

PROJECT AREA MAP

WAVERLY ROAD DOCUMENTS

CONTRACT 3-4-5  BID DOCUMENTS